HAZ was engaged to conduct a pre-hazardous areas audit on two IECEx certified overhead cranes, which are to be installed in a Zone 22 area of a power station.
The auditor had worked with the client on other cranes they had installed, and at the time they were already in their final locations, meters above the ground in dust filled environments, requiring the correct inductions, permits, paperwork and operations approval before the audit could take place.
Some lessons learnt from this experience include:
The client took these learnings from the inspections and made a key
decision to have the overhead cranes inspected before mobilising to site. Apart from some loose terminals, cable bending radius issues and
incorrectly certified adaptors and glands, the time it took to inspect the two overhead cranes was significantly reduced.
Those items required for remediation were order and will arrive to be installed before the installation occurs on site.
Early engagement of an Auditor to inspect and confirm the equipment is correct prior to it going to site, will significantly reduce the time and cost of the project.
Now they have the peace of mind that the equipment is ready to be installed and that there will be no surprises when it comes to the final
Audit prior to energisation.
This material is produced by HAZ. The information is of a general nature only and should not be relied upon. Each set of circumstances associated with compliance of hazardous areas and Type B compliance is unique and expert advice on your particular circumstances should be sought. HAZ accepts no liability for any reliance on the information published on this website.